Engineering services across different phases, including pre-commissioning, commissioning, and start-up, for water, tailings, concentrate, and slurry transportation systems.
Project

Engineering EIA for Existing 7″ Concentrate Pipeline Bypass

Client

Collahuasi Mining Company Doña Ines

Location

Chile

Type of service​

Engineering EIA

In 2015, Collahuasi Mining Company requested BRASS to develop engineering suitable for the inclusion and preparation of an Environmental Impact Assessment (EIA) demonstratng compliance continuity with information provided for the elaboration of the applicable Environmental Sectoral Permits for the design of the 7″ concentrate pipeline bypass, considering the avoidance of the area of designated and estimated dump zone expansions.

Fluid type

Slurry Pipeline

Pipe lenght

10 KM

Diameter

7″