BRASS conducted a feasibility study to confirm the technical and operational viability of the system, building on the pre-feasibility engineering work carried out in 2021.
BRASS was tasked with identifying the work needed to rehabilitate the tailings transport system and enable the transport of ore in a mixture of gypsum, sand, and reprocessed slurry.
The project is part of an initiative to remove tailings from one of the mining company's tailings ponds, which involved reprocessing, pumping, thickening, and transporting the removed material.
The solution took into account the following: transportation systems involved, via 24-inch pipelines, to transport part of the material to another tank and pulp to the flotation area.